New concrete must be cured for 28 days and have a moisture content
of less than 5% before laying with POLYFILLER/PR 20 The substrate
must have a minimum, compressive strength of 25 N/mm² and
minimum pull off strength of 1.5 N/mm².
Substrate should be fine - gripping and solid, free from loose and
friable particles, surface laitance, dust, oil, grease, previous coatings.
Concrete substrate should be prepared by a suitable sand - blasting technique using either a captive, vacuum blasting machine or similar mechanical means.
Small areas where oil or grease persist should be treated with
chemical degreaser.
Large areas of such contamination must be removed by flame cleaning. All dust and other debris from the preparation process must be removed prior to continuing with the work.
|